|
These discoveries have raised concerns about the structural integrity of
reactor penetration nozzles in the top of reactor pressure vessels at PWRs
throughout the industry. Control rod drive shafts pass through penetration
nozzles which sit at the top of a reactor vessel head. Control rod drive
mechanisms (CRDMs) are used to guide the movement of control rods in and out of
a reactor core. Axial cracking (along the length) of these nozzles has previously been
observed but not considered a safety concern requiring immediate attention. This
issue was addressed by the NRC in Generic Letter 97-01, issued in 1997.
Inspections and repairs have generally been made during plant maintenance
outages. However, in 2001, circumferential cracking (part way around the width
of the nozzle, above the structural retaining weld) was discovered at several
PWRs.
One function of the nozzles is to maintain the reactor coolant system
pressure boundary. Cracking of the control rod drive mechanism nozzles represent
a degradation of the primary reactor coolant system boundary, and hence, is
potentially safety significant.
NRC requested information from PWR licensees to determine whether current
inspection practices are adequate and whether any additional regulatory response
by the agency is necessary.
The NRC bulletin requested PWR licensees to provide information related to
the structural integrity of these reactor pressure vessel head penetration
nozzles, "as needed to ensure the integrity of their reactor coolant system
pressure boundaries and demonstrate compliance with applicable regulatory
requirements." The bulletin also required that PWR licensees submit a written
response indicating whether the requested information will be submitted within
the required 30-day time period. NRC licensees unable to satisfy this
requirement had to submit a written description of any alternative course of
action they proposed to take, including the basis for its acceptability.
Hot Leg Axial Cracking at the V.C. Summer Nuclear
Station
The hot leg weld axial cracking was identified at V.C. Summer on October 7,
2000, during a normally scheduled inspection of the V.C. Summer containment
after entering a refueling outage. The licensee found over 200 pounds of boric
acid crystals on the containment floor and protruding from the air boot around
the "A" loop reactor coolant system (RCS) hot leg pipe. Examinations showed a
short through-wall axial crack in the hot leg nozzle safe end weld,
approximately 3 feet from the reactor vessel. Additional examinations of the
other 5 nozzle safe end welds found crack indications but no through-wall
cracks. A 12-inch long section of the hot leg pipe containing the leaking weld
was replaced with a new section of stainless steel pipe and Alloy 52/152 welds.
The remaining weld indications were analyzed and found to be safe for another
cycle of operation.
In a letter dated December 14, 2000, Mr. David J. Modeen of the Nuclear
Energy Institute (NEI) informed Dr. Brian W. Sheron of the NRC that the EPRI
Materials Reliability Project (MRP) intended to lead the industry's actions to
address the generic implications of the cracking seen at V.C. Summer. The MRP is
a utility-directed oversight organization of the PWR Owners Group whose purpose
is to address and resolve, on a consistent industry-wide basis, PWR
material-related issues.
CRDM Nozzles Circumferential Cracking at Oconee Nuclear
Station
Cracking in the Control Rod Drive Mechanism (CRDM) nozzles and seal welds at
Oconee Nuclear Station was first noted on Unit 1 when small amounts of boron
residue was found on the top of the reactor pressure vessel (RPV) head in
November 2000, during a refueling outage inspection. Similar problems were found
on Unit 3 in February 2001, during a planned maintenance outage, and on Unit 2
in May 2001, during a refueling outage. Subsequent examinations of the CRDM
nozzles with boron residue found through-wall axial cracking in these nozzles,
and through-wall circumferential cracking above the weld in two of nozzles in
Unit 3, and in one nozzle in Unit 2.
Since April 2001, the NRC staff has held a series of public meetings with the industry at NRC
Headquarters to discuss Circumferential Cracking of CRDM Nozzles.
|